GARDEN ROUTE | KAROO NEWS - Stage 6 load-shedding will be implemented at 05:00 until further notice. This is due to failures of generating units at Tutuka, Kriel, Duvha and Kendal power stations since yesterday.
Eskom will publish a further update as soon as significant changes occur.
Eskom has urged South Africans to use electricity sparingly during this period. “We thank those South Africans who do heed the call to use electricity sparingly and efficiently in helping to alleviate the pressure on the power system, as this is assisting in avoiding higher stages of load-shedding,” the power utility said.
Receive Eskom load-shedding notifications by downloading the free EskomSePush app from Google Play Store at https://sepush.co.za/
You will be affected as follows:
George
- Friday 21 April: 04:00 - 06:30 | 12:00 - 16:30** | 20:00 - 22:30
- Saturday 22 April: 04:00 -06:30 | 12:00 -16:30 | 20:00 - 00:30
- Sunday 23 April: 04:00 - 06:30 | 12:00 -14:30 | 20:00 - 22:30
Uniondale
- Friday 21 April: 07:00 - 11:30 | 15:00 - 19:30** | 23:00 - 01:30
- Saturday 22 April:07:00 - 09:30 |15:00 -19:30 | 23:00 - 03:30
- Sunday 23 April: 07:00 - 09:30 |15:00 - 17:30| 23:00 - 03:30
Sedgefield
- Friday 21 April: 04:00 - 06:30 | 12:00 - 16:30** | 20:00 - 22:30
- Saturday 22 April: 04:00 -06:30 | 12:00 -16:30 | 20:00 - 00:30
- Sunday 23 April: 04:00 - 06:30 | 12:00 -14:30 | 20:00 - 22:30
Knysna | Plettenberg Bay
- Friday 21 April: 02:00 -06:30 | 10:00 - 12:30 | 18:00 -20:30
- Saturday 22 April:02:00 - 06:30 | 10:00 - 14:30 | 18:00 - 20:30
- Sunday 23 April: 02:00 - 04:30 | 10:00 -14:30 | 18:00 - 22:30
Mossel Bay
- Friday 21 April: 02:00-06:30 | 10:00- 12:30 |18:00 -20:30
- Saturday 22 April: 02:00- 06:30 | 10:00-14:30 | 18:00-20:30
- Sunday 23 April: 02:00- 04:30 | 10:00 - 14:30 |18:00 -22:30
Albertinia | Riversdale | Gouritsmond | Stilbaai | Melkhoutfontein | Jongensfontein
- Friday 21 April: 02:00 -06:30 | 10:00-12:30 | 18:00-20:30
- Saturday 22 April: 02:00-06:30 | 10:00- 14:30 | 18:00- 20:30
- Sunday 23 April: 02:00 - 04:30 | 10:00 -14:30 |18:00 - 22:30
Heidelberg | Slangrivier
- Friday 21 April: 00:00 - 04:30 | 08:00 - 12:30 | 16:00 - 18:30
- Saturday 22 April: 00:00 - 02:30| 08:00 - 12:30 | 16:00 - 20:30
- Sunday 23 April: 00:00 - 02:30| 08:00 - 10:30 | 16:00 - 20:30
Oudtshoorn
- Friday 21 April: 02:00-04:30 | 10:00-12:30 | 18:00-22:30
- Saturday 22 April: 02:00-06:30 | 10:00-12:30 | 18:00-20:30
- Sunday 23 April: 02:00 - 06:30 | 10:00 - 14:30 |18:00 -20:30
Graaff-Reinet
- Friday 21 April: 01:00 - 05:30 |09:00 - 11:30 | 17:00-19:30
- Saturday 22 April:01:00- 05:30 | 09:00-13:30 |17:00-19:30
- Sunday 23 April: 01:00- 03:30 | 09:00-13:30 | 17:00-21:30
Consumers are urged to turn off high-usage equipment and where possible to not switch on appliances such as stoves and kettles for at least 30 minutes after load-shedding.