GARDEN ROUTE NEWS - Due to unusually high demand and the breakdown of a generating unit each at Hendrina, Kendal and Kriel power stations, load shedding has been escalated to Stage 5 until further notice.
You will be affected as follows:
George:
- Saturday 10 December: 02:00 - 04:30 | 10:00 - 12:30 | 18:00 - 20:30
- Sunday 11 December: 02:00 - 06:30 | 10:00 - 12:30 | 18:00 - 20:30
- Monday 12 December: 02:00 - 04:30 | 10:00 - 14:30 | 18:00 - 20:30
Uniondale:
- Saturday 10 December: 05:00 - 07:30 | 13:00 - 15:30 | 21:00 - 23:30
- Sunday 11 December: 05:00 - 09:30 | 13:00 - 15:30 | 21:00 - 23:30
- Monday 12 December: 05:00 - 07:30 | 13:00 - 17:30 | 21:00 - 23:30
Sedgefield:
- Saturday 10 December: 02:00 - 04:30 | 10:00 - 12:30 | 18:00 - 20:30
- Sunday 11 December: 02:00 - 06:30 | 10:00 - 12:30 | 18:00 - 20:30
- Monday 12 December: 02:00 - 04:30 | 10:00 - 14:30 | 18:00 - 20:30
Knysna | Plettenberg Bay:
- Saturday 10 December: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 20:30
- Sunday 11 December: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 18:30
- Monday 12 December: 00:00 - 04:30 | 08:00 - 10:30 | 16:00 - 18:30
Mossel Bay:
- Saturday 10 December: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 20:30
- Sunday 11 December: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 18:30
- Monday 12 December: 00:00 - 04:30 | 08:00 - 10:30 | 16:00 - 18:30
Albertinia, Riversdale, Gouritsmond, Stilbaai, Melkhoutfontein, Jongensfontein:
- Saturday 10 December: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 20:30
- Sunday 11 December: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 18:30
- Monday 12 December: 00:00 - 04:30 | 08:00 - 10:30 | 16:00 - 18:30
Heidelberg, Slangrivier:
- Saturday 10 December: 06:00 - 08:30 | 14:00 - 16:30 | 22:00 - 00:30
- Sunday 11 December: 00:00 - 02:30 | 06:00 - 08:30 | 14:00 - 16:30 | 22:00 - 00:30
- Monday 12 December: 06:00 - 10:30 | 14:00 - 16:30 | 22:00 - 00:30
Witsand:
- Saturday 10 December: 02:00 - 05:00 | 10:00 - 12:30 | 18:00 - 20:30
- Sunday 11 December: 02:00 - 04:30 | 10:00 - 14:30 | 18:00 - 20:30
- Monday 12 December: 02:00 - 04:30 | 10:00 - 12:30 | 18:00 - 22:30
Very important:
Use only essential appliances when the power is restored.
Consumers are reminded to use electricity sparingly especially when power returns after load shedding. This will reduce the risk of overload tripping on the network.
Consumers are requested, where possible to not switch on appliances such as stoves and kettles for at least 30 minutes after load shedding.