LOAD SHEDDING NEWS - On Wednesday and Thursday, Stage 1 load shedding will be implemented from 05:00 until 16:00, followed by Stage 3 load shedding from 16:00 until midnight on both days.
The implementation of Stage 1 load shedding is due to an increase in generation unit failures.
Load shedding will be suspended from midnight on Thursday until 16:00 on Friday and Stage 3 load shedding will be implemented again from 16:00 until midnight.
You will be affected as follows:
George:
- Wednesday 5 July: 20:00 - 22:30
- Thursday 6 July: 20:00 - 22:30
- Friday 7 July: 20:00 - 22:30
Uniondale:
- Wednesday 5 July: 16:00 - 17:30 | 23:00 - 00:30
- Thursday 6 July:16:00 - 17:30 | 23:00 - 00:30
- Friday 7 July: 23:00 - 00:30
Sedgefield:
- Wednesday 5 July: 20:00 - 22:30
- Thursday 6 July: 20:00 - 22:30
- Friday 7 July: 20:00 - 22:30
Knysna | Plettenberg Bay:
- Wednesday 5 July: 10:00 - 12:30
- Thursday 6 July: 18:00 -20:30
- Friday 7 July: 18:00 - 20:30
Mossel Bay:
- Wednesday 5 July: 10:00 - 12:30
- Thursday 6 July: 18:00 -20:30
- Friday 7 July: 18:00 - 20:30
Albertinia | Riversdale | Gouritsmond | Stilbaai | Melkhoutfontein | Jongensfontein:
- Wednesday 5 July: 10:00 - 12:30
- Thursday 6 July: 18:00 -20:30
- Friday 7 July: 18:00 - 20:30
Heidelberg | Slangrivier:
- Wednesday 5 July: 16:00 - 18:30
- Thursday 6 July: 16:00 - 18:30
- Friday 7 July: 16:00 - 18:30
Oudtshoorn:
- Wednesday 5 July: 18:00 - 20:30
- Thursday 6 July: 10:00 - 12:30
- Friday 7 July: 18:00 - 20:30
Graaff-Reinet:
- Wednesday 5 July: 09:00 - 11:30
- Thursday 6 July: 17:00 - 19:30
- Friday 7 July: 17:00 - 19:30
Consumers are reminded to use electricity sparingly after power returns.
Please do not switch high-usage equipment on immediately after load shedding.
Receive Eskom load shedding notifications by downloading the free EskomSePush app from Google Play Store at https://sepush.co.za/