GARDEN ROUTE | KAROO NEWS - Stage 4 load shedding will continue to be implemented until 05:00 on Saturday, with varying stages of load shedding implemented until 05:00 on Monday.
Receive Eskom load shedding notifications by downloading the free EskomSePush app from Google Play Store at https://sepush.co.za/
You will be affected as follows:
GEORGE:
- Friday 28 July: 18:00 - 20:30
- Saturday 29 July: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 18:30
- Sunday 30 July: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 18:30
UNIONDALE:
- Friday 28 July: 21:00 - 23:30
- Saturday 29 July: 03:00 - 05:30 | 11:00 - 13:30 | 19:00 - 21:30
- Sunday 30 July: 03:00 - 05:30 | 11:00 - 13:30 | 19:00 - 21:30
SEDGEFIELD:
- Friday 28 July: 18:00 - 20:30
- Saturday 29 July: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 18:30
- Sunday 30 July: 00:00 - 02:30 | 08:00 - 10:30 | 16:00 - 18:30
KNYSNA | PLETTENBERG BAY:
- Friday 28 July: 16:00 - 18:30
- Saturday 29 July: 14:00 - 16:30 | 22:00 - 00:30
- Sunday 30 July: 06:00 - 08:30 | 22:00 - 00:30
MOSSEL BAY:
- Friday 28 July: 16:00 - 18:30
- Saturday 29 July: 14:00 - 16:30 | 22:00 - 00:30
- Sunday 30 July: 06:00 - 08:30 | 22:00 - 00:30
ALBERTINIA | RIVERSDALE | GOURITSMOND | STILBAAI | MELKHOUTFONTEIN | JONGENSFONTEIN:
- Friday 28 July: 16:00 - 18:30
- Saturday 29 July: 14:00 - 16:30 | 22:00 - 00:30
- Sunday 30 July: 06:00 - 08:30 | 22:00 - 00:30
HEIDELBERG | SLANGRIVIER:
- Friday 28 July: 22:00 - 00:30
- Saturday 29 July: 04:00 - 06:30 | 20:00 - 22:30
- Sunday 30 July: 04:00 - 06:30 | 12:00 - 14:30 | 20:00 - 22:30
OUDTSHOORN:
- Friday 28 July: 16:00 - 18:30
- Saturday 29 July: 06:00 - 08:30 | 14:00 - 16:30 | 22:00 - 00:30
- Sunday 30 July: 22:00 - 00:30
GRAAFF-REINET:
- Friday 28 July: 23:00 - 01:30
- Saturday 29 July: 13:00 - 15:30 | 21:00 - 23:30
- Sunday 30 July: 05:00 - 07:30 | 21:00 - 23:30
Consumers are reminded to use electricity sparingly after power returns
Please do not switch high-usage equipment on immediately after load shedding. Consumers are urged to turn off high-usage equipment and where possible to not switch on appliances such as stoves and kettles for at least 30 minutes after load shedding.
This will reduce the risk of overload tripping on the network and reduce our current high MVA spikes.
‘We bring you the latest Garden Route, Hessequa, Karoo news’